UProcess

ModulesTask Risk AssessmentWork Control

The risk of today’s task, before it starts.One assessment, read and signed by the crew at the job.

For supervisors and crews doing non-routine work: start from your company’s task library or a blank sheet, rate each hazard on your own risk matrix, and send back what the crew adds at the job. With a permit or without one.

TRA-2026-0088 · reviewed at the job. A snapshot of v2 for this job. The crew read it on the roof, signed, and added the step the stair needed.

TRA-2026-0088 · Welding on the roof of tank T-201
TRA-2026-0088 · reviewed at the job
For · PTW-2026-0142Template · Welding at height on a tank roof · v2Matrix · Corporate 5×5 · published 12 Aug 2026Date · 12 Nov 2026
No.StepHazardControlsBefore → after
1
Climb the stair to the roof with tools
Fall at the roof edge; dropped tools
Engineering
Fixed stair handrail; temporary edge rail, north quadrant
Administrative
Exclusion zone below the work
S3·L3 · Medium→ S3·L1 · Low
2
Lift tools and cables by hand line and bagAdded by the crew 07:08
Loss of balance on the stair; dropped load
Engineering
Tool bag and hand line from the roof; tag line for cables
S3·L3 · Medium→ S3·L1 · Low
3
Set fire protection and spark containment
Sparks falling to the tank shoulder and the dike
Engineering
Fire blanket under the weld; spark screen at the roof edge
Administrative
Combustibles cleared 11 m; drains covered 15 m
S4·L3 · High→ S4·L1 · Low
4
Test the vapour space and the work point
Flammable vapour inside the tank or at the arc
Elimination
Fill line spaded, pump locked off (ISO-2026-0031)
Administrative
Gas test before work and every hour; stop at 10% LEL
S5·L3 · High→ S5·L1 · Medium
5
Weld the handrail to the brackets
Burns, welding fume, ignition of residue
Engineering
Local fume extraction
Administrative
Fire watch during and 30 min after
PPE
Welding PPE, face shield
S4·L4 · High→ S4·L1 · Low
6
Grind the welds
Sparks travel further than when welding; eye injury
Engineering
Spark screen turned to the grinding direction
PPE
Face shield over glasses
S3·L3 · Medium→ S3·L1 · Low
7
Clear the roof; fire watch stays
Smouldering residue after the crew leaves
Administrative
Fire watch 30 min after the last weld; hand-back checklist
S4·L2 · Medium→ S4·L1 · Low

Crew review · 07:10 at the roof · 1 step added at the job

Carlos Mendes
Arden Welding · holder · 07:10
Rafael Okonkwo
Arden Welding · 07:10
Ana Lima
Fire watch and gas tester · 07:11
Action
AT-0157 · Fit a permanent tool hoist point on the T-201 roof · Open

One task, three views. Switch the view: the steps, the crew review and the proposal change; nothing is retyped. An example assessment; the fields are the product’s, the values illustrative.

TRA-2026-0088 · step 5 of 7
Weld the handrail to the bracketsBurns, welding fume, ignition of residue
Engineering
Local fume extraction
Administrative
Fire watch during and 30 min after
PPE
Welding PPE, face shield
Risk
S4·L4 High → S4·L1 Low
Crew review · 07:10 at the roof
1 step added at the job

Where it connects

Risk MatrixTask Risk AssessmentAction TrackingVerified

On the same loop: Permit to Work, Hazard & Risk Register, Contractor Management and 38 more modules in one workspace.

Method note

Start from the library, or from a blank sheet? Both schools have a point.

Templates keep the controls that took years to learn. Blank sheets keep people thinking about today.

Leandro · Founder, UProcess

One school standardises: the same task gets the same analysis, written once by the people who know it best. The other warns that a reused analysis stops describing the job in front of the crew, and wants every job to start fresh. Each is right about the other’s failure.

So the crew starts from either, and the library learns from the job.

  • From the libraryA snapshot of the company template. Later versions of the template never change it.
  • BlankFor a one-off job the library does not cover yet.
  • Proposed backA step the crew adds at the job is marked, and can go to the task owner as the next version.

Where Task Risk Assessment usually breaks

Four places a task assessment goes wrong, and what the record does about each.

01

Written in the office, without the crew.

OSHA’s guide to job hazard analysis calls employee involvement very important: the people doing the job understand it best, and taking part in every step reduces oversights.

Source: OSHA 3071, Job Hazard Analysis

In UProcess The crew reviews the assessment at the job: who was present, and the review signed by the person who led it. A permit that requires an assessment counts it only after that review.

Crew review · TRA-2026-0088

Carlos MendesArden Welding
Present
Rafael OkonkwoArden Welding
Present
Ana LimaFire watch
Present
Tomás RuizNamed on the permit
Not present

1 step added at the job

02

Copied from the last job.

HSE’s permit-to-work guidance says precautions such as process or electrical isolation must be identified in task risk assessments before any work is undertaken, by people who have thought about the foreseeable risks of that job.

Source: HSE, Guidance on permit-to-work systems (HSG250)

In UProcess An assessment starts as a snapshot of a versioned template, and a step the crew adds at the job is marked as added there. The task owner can accept it into the next version, so the library follows the work.

Step 2 · added at the job

Step
Lift tools and cables by hand line and bag
Why
Stair too narrow to climb with cable and grinder
In library v2
No
Proposal
Sent 12 Nov 2026 to Priya Nair, task owner

Accepted, it becomes v3. TRA-2026-0088 keeps its own snapshot.

03

Controls slide to the bottom of the hierarchy.

NIOSH ranks controls from elimination and substitution down to administrative controls and PPE, the least effective, and asks workplaces to apply them in that order. A task analysis that lists only procedures and PPE still looks complete on paper.

Source: NIOSH, hierarchy of controls

In UProcess Every control is labelled by its level in the hierarchy. A step held only by procedures and PPE reads that way on the page the crew signs.

Step 4 · flammable vapour at the arc

Elimination
Fill line spaded, pump locked off (ISO-2026-0031)
Substitution
—
Engineering
—
Administrative
Gas test before work and every hour; stop at 10% LEL
PPE
—

Each control shows its level. Empty levels stay visible.

04

Rated on a scale nobody else uses.

A systematic review of job safety analysis found that it offers no unified framework for rating risk, so methods differ from one analysis to the next.

Source: Ghasemi et al., Safety and Health at Work (2023)

In UProcess Each hazard is rated before and after controls on your company’s published Risk Matrix version, and the version stays with the assessment. With no published matrix, the assessment says hazards are not rated.

Corporate 5×5 · published 12 Aug 2026

Before · S5·L3 · HighAfter · S5·L1 · Medium

Step 4 · the version used stays on the assessment.

Assessment TRA-2026-0088 · for PTW-2026-0142 · 12 Nov 2026

PersonCompanyRolePresent
Carlos MendesArden WeldingHolder
Rafael OkonkwoArden WeldingWelder
Ana LimaSiteFire watch, gas tester
Tomás RuizArden WeldingWelder
Review signed
07:10 · Carlos Mendes · confirmed on device
Added at the job
Step 2 · 07:08
Library
Proposed as v3 · waiting for the task owner

The record an auditor asks for.

An assessment is worth what the crew read and signed, at the job, on the day.

  • The template and version the assessment started from.
  • Ratings before and after controls, with the matrix version used.
  • Who was present at the job, and who signed the review and when.
  • What the crew added, and whether the library took it.

What’s in an assessment

Structure
Task → steps → hazards → controls, each control labelled elimination, substitution, engineering, administrative or PPE.
Library
Your company’s task templates, versioned. An assessment is a snapshot; later versions never change it.
Rating
Before and after controls, on the published Risk Matrix version, kept on the assessment.
Crew review
Who was present, the steps added at the job, and a signed review.
Links
The permit’s assessment gate, controls not yet in place as actions in Action Tracking, and the site activity in the Hazard & Risk Register.

Questions

Do I need a permit to use it?

No. An assessment can stand alone. Work without a permit still deserves a task analysis.

What if we have no risk matrix yet?

The assessment still works, without ratings, and says so: hazards not rated. Publish a matrix and new assessments are rated on it.

Does a high residual rating block the permit?

No. The permit’s assessment gate asks only that the assessment is linked and reviewed by the crew.

Who changes the library?

The task owner. Steps proposed from the field wait for them, and an accepted change becomes a new version of the template.

Your next job, assessed by the people doing it.

Start free →No account needed to start. Keep your work when you’re ready.