Safe to start up, item by item.One review, from the first question to the start-up decision.

For start-up leads and process safety engineers: review against your form, class every finding before or after start-up, have a separate team validate, and authorize start-up only when the review reads ready. Readiness is worked out from the answers, never typed.

Not ready. One question not verified and one before-start-up action open. Readiness is worked out, never typed.

PSSR-2026-0007 · Return to service of FV-1410 and the V-201 propane feed
North site · Propane vaporizer area · basis MOC-2026-0031 · planned start-up 6 Nov 2026
Not ready
Type · ModificationForm · Process modification review · v3
SectionApplicableYesNoN/ANot verified
Design and installationYes9010
Instruments and protectionsYes11101
ProceduresYes6010
TrainingYes4000
Process safety informationYes5110
Emergency responseYes3030
Civil and structuralNo————
Total38261

Not ready · 1 not verified · 1 before-start-up action not done

FindingQuestionAnswerAction
F-1PSHH-1405 trip tested at its set point after the valve changeNoAT-0203 · before start-up · Done
F-2P&ID 101 updated to the new valve trimNoAT-0204 · after start-up · Open · due 20 Nov 2026

Start-up authorization · Not available while the review reads not ready.

The same review, from the first answers to the start-up decision. An example review; the fields are the product’s, the values illustrative.

PSSR-2026-0007 · basis MOC-2026-0031
Not readyNot ready · 1 not verified · 1 before-start-up action not done
Answers
38 yes · 2 no · 6 n.a. · 1 not verified
Holding it
LAH-201 test not verified
Before start-up
AT-0203 · open
Planned start-up
6 Nov 2026

Where it connects

Management of ChangePre-Startup Safety ReviewAction TrackingVerified

On the same loop: Workforce and 40 more modules in one workspace.

Method note

Every item closed before start-up, or only the ones that matter? Both schools are right.

Zero open items sounds safe, until a missing label holds a unit down for a week and the list stops meaning anything.

Leandro · Founder, UProcess

One school starts up only with an empty list, so nobody has to judge what can wait. The other splits the punch list: what must be done before energy or material goes in, and what can follow start-up with an owner and a date.

So each action says when it must be done, and only the before-start-up ones hold the decision.

  • Before start-upKeeps the review not ready until the work is done.
  • After start-upTracked with an owner and a date. It never holds the decision.
  • Not verifiedCounts as not ready. A tick without a check is not an answer.

Where Pre-Startup Safety Review usually breaks

Four places a start-up review goes wrong, and what the record does about each.

01

Start-up before the review is finished.

At Bayer CropScience in 2008, under pressure to resume production, the unit was started before the pre-startup safety review was complete and before valve lineups and equipment checkouts were finished.

Source: U.S. Chemical Safety Board

In UProcess Start-up authorization is its own decision, made after validation, and it cannot be granted while the review reads not ready.

Start-up authorization · PSSR-2026-0007

Not available The review reads not ready.

  • 1 question not verified · LAH-201 high-level alarm tested
  • 1 before-start-up action not done · AT-0203

Validation approves the review. Authorization is a second decision.

02

Signed off as if it were done.

Before the Texas City isomerization unit was restarted in 2005, CSB investigators found instrument checks required by the start-up procedure were skipped and signed off as if done, with the level indicator and level alarm already faulty.

Source: U.S. Chemical Safety Board, preliminary findings

In UProcess Not verified is an answer of its own. An applicable required question left unanswered or not verified keeps the review not ready, and each answer can carry its comment and evidence.

Instruments and protections · 3 of 13

LT-201 level transmitter calibratedCalibration sheet CAL-2026-118 attached
Yes
LAH-201 high-level alarm testedEvidence required · none attached
Not verified
PSHH-1405 trip tested at set pointFinding F-1 raised
No

Not verified keeps the review not ready, like an unanswered required question.

03

A known fault waved through to after start-up.

OSHA’s process safety standard asks for equipment deficiencies outside acceptable limits to be corrected before further use, or later only in a safe and timely manner while other means keep the operation safe.

Source: OSHA 29 CFR 1910.119(j)(5), equipment deficiencies

In UProcess A no or not verified answer raises a finding, and each finding needs an action before the review can be submitted. Each action is classed before or after start-up and goes to Action Tracking with an owner and a due date.

Action Tracking · AT-0203

Test PSHH-1405 at its set point after the FV-1410 change

Owner
Liam O’Connor
Due
5 Nov 2026
Start-up impact
Before start-up
From
Pre-Startup Safety Review · PSSR-2026-0007 · F-1
Check that it worked

Trip proven at 18.5 barg · test record attached · checker James Walker

04

A partial review passes as a complete one.

At Williams Olefins, the CSB lists an incomplete pre-startup safety review among the process safety failures that came before the 2013 reboiler rupture.

Source: U.S. Chemical Safety Board

In UProcess Applicable sections are set for each review, and a readiness summary counts yes, no, not applicable and not verified before validation. A separate validation team approves, or returns the review with a reason, and each return adds a revision.

Readiness summary · before validation

YesNoN/ANot verified
Answers38261
Findings, before start-up1
Findings, after start-up1
Prepared
0
Sent to Action Tracking
2
Done
1

6 of 7 sections applicable. Civil and structural marked not applicable for this review.

Review PSSR-2026-0007Basis MOC-2026-0031Form Process modification review · v3

DecisionByRoleDate
Submitted for validation · revision 1James WalkerReview lead3 Nov 2026
Returned · “Pressure test record for FV-1410 missing”Emma ClarkeValidation4 Nov 2026
Submitted for validation · revision 2James WalkerReview lead5 Nov 2026
ApprovedEmma ClarkeValidation5 Nov 2026
Start-up authorizedDaniel OkaforStart-up authority6 Nov 2026 · 14:10

The record an auditor asks for.

Who reviewed, who validated and who authorized: three decisions, each with a name and a date.

  • The review team and its sessions, and the basis of the review: the MOC case and the drawings, studies and procedures behind it.
  • Every answer with its comment and evidence, against the form version the review started from.
  • Each validation decision, including returns with their reason and the revision they started.
  • The start-up authorization, with who decided, when, and the planned and actual start-up dates.

What’s in a review

Scope
The type of start-up, such as a modification or a restart after shutdown, the system under review, its boundary, and the basis: the MOC case and the documents behind it.
Form
Taken from your form library and fixed in the review when it starts, so a later edit of the form never changes it. Sections are marked applicable per review.
Answers
Yes, no, not applicable or not verified, each with a comment and evidence. A question can be set to require evidence.
Findings
Raised by a no or not verified, each with actions classed before or after start-up and sent to Action Tracking.
Decisions
Readiness worked out from the answers and actions; validation by a separate team; start-up authorized or not authorized, with planned and actual dates.

Questions

Can we start up with open items?

Yes, when they are classed after start-up. They stay in Action Tracking with an owner and a date, and they never hold the decision.

Who validates a review?

The validation team you name for that review. It is separate from the review team, though the same person may sit on both.

Is approving the review the same as authorizing start-up?

No. Validation approves the review. Start-up authorization is a separate decision, recorded with who made it and when.

Can we use our own checklist?

Yes. Write your forms in the form library; each review keeps the version it started from.

Your next start-up, decided on the record.