Authorised work, here and now.One permit, from the request to the closed site.

For area authorities, permit holders and the EHS lead who has to show control of work: each permit type sets its gates, and a permit goes active only when every gate is met. The same record on the phone at the job and on the plant board.

Active since 07:30. Every gate met at activation. Gas re-tests fall due on the plan’s clock; the next one shows on the permit.

PTW-2026-0142 · Weld 12 m of new handrail to roof brackets
Hot work v3 (company) · T-201 · roof · north quadrant · Tank farm · 12 Nov 2026 · Day shift · 07:00–19:00
Active since 07:30
Requested · 06:50 · Carlos MendesPrepared · 07:05–07:20 · isolation, TRA, field checkAuthorised · 07:22 · Thiago MoreiraActive · current · since 07:30Handed back · —Closed · —

8 of 8 gates met · gas re-test due 15:30

Holder
Carlos Mendes · Arden Welding
Authoriser
Thiago Moreira · area authority
Work order
WO 48213
GateStateReasonWho
Field check with the holderDone 07:15Combustibles cleared 11 m; drains within 15 m coveredThiago Moreira · Carlos Mendes
Isolation held and provenHeldISO-2026-0031 · 3 of 3 points provenLucas Almeida · isolating authority
Gas test in rangeIn range0% LEL at 14:30, work point and vapour spaceAna Lima · gas tester
Named roles presentPresentSigned present 07:24Ana Lima · fire watch
Competence validValidHot work · valid to 10 Jan 2027Read from Training
Contract eligibilityEligibleArden Welding · CT-2026-014Read from Contractor Management
Task assessment attachedReviewedTRA-2026-0088 · reviewed at the job 07:10Carlos Mendes · crew of 3
No conflicting workMet · 1 heldPTW-2026-0147 drain and vent T-202 is held, not authorisedCompatibility rules

Gas plan · LEL alarm 5% · stop 10% · O₂ 19.5–23.5% · re-test every hour

07:28
0% LEL
08:30
0% LEL
09:30
1% LEL
10:30
0% LEL
11:30
1% LEL
12:30
0% LEL
13:30
0% LEL
14:30
0% LEL

Alarm 5% · Stop 10%

What the plant knows about T-201
Process Hazard Identification
Tank farm node · hot work during filling rated in the top band · 1 open recommendation
Bypass Control
BYP-2026-0008 · LSHH-201 on T-201 bypassed for its function test · 3 h of 4
Chemical Management
At T-201: diesel (flammable)
Energy Isolation
ISO-2026-0031 · held · 3 locks on

One permit, three moments in its day. Switch the state: the gates, the gas strip and the answer change. An example permit; the fields are the product’s, the values illustrative.

PTW-2026-0142 · Hot work v3
T-201 · roof · north quadrantCarlos Mendes · Arden Welding
8 of 8 gates met · gas re-test due 15:30
Gates
8 of 8 met
Isolation
ISO-2026-0031 · held
Last gas
0% LEL · 14:30
Next re-test
15:30
Fire watch
Ana Lima · present

Where it connects

Energy IsolationPermit to WorkAction TrackingVerified

On the same loop: Task Risk Assessment, Confined Spaces, Contractor Management and 38 more modules in one workspace.

Method note

Test the gas once, or keep testing? Both are in use, for different jobs.

A test before work proves the start of the job. Only readings during the work prove the middle.

Leandro · Founder, UProcess

Many sites test once before hot work and again after a break. Investigators keep asking for readings during the work as well, inside the vessel and not only at the arc, because conditions change after the permit is signed. Which one is right depends on what is behind the work point.

So each permit type sets its own gas plan.

  • Before workA reading for every gas in the plan, inside the plan’s window, before the permit can go active.
  • At an intervalRe-tests fall due on the plan’s clock and show as due to the gas tester.
  • From a monitorA detector attached to the permit sends readings. A reading at the stop limit suspends the permit.

Where Permit to Work usually breaks

Four places a permit goes wrong, and what the record does about each.

01

The signer does not know the process.

At a chemical plant in Buffalo, the people who signed a contractor’s hot work permit were not familiar with the process connected to the tank. The air above the tank was tested; the vapour inside it was not. The explosion was fatal.

Source: U.S. Chemical Safety Board, DuPont Buffalo

In UProcess Before signing, the authoriser sees what the plant already knows about the equipment tag: hazard study scenarios, past investigations, barrier elements on the tag, live bypasses, held isolations and the chemicals at the work point.

What the plant knows about T-201 · before you sign

Hazard study
Hot work during filling · top band · 1 open recommendation
Investigation
Public case · similar equipment · tank roof explosion during welding
Bypass
LSHH-201 bypassed · BYP-2026-0008 · 3 h of 4
At the work point
Diesel (flammable)

Read by equipment tag at the moment of signing. Each item opens in its own module.

02

The shift changes, the permit does not.

Many accidents start with a failure of communication at shift handover, most of them during planned maintenance. The Piper Alpha inquiry named it among the causes.

Source: HSE, human factors: shift handover

In UProcess A permit is valid for one shift. Before the change, the incoming area authority revalidates it: the holder and crew confirmed, a new gas test where the type asks, and a signature. A permit not revalidated is suspended.

Shift change 19:00 · PTW-2026-0142

18:40
Revalidation due · Rafael Santos, night area authority
18:48
Field check at the roof
18:52
Gas 0% LEL · Ana Lima
18:55
Revalidated · signed, confirmed on device

Not revalidated by the change: suspended. Nothing continues on its own.

03

The gas is tested once, then trusted.

After a series of fatal explosions during hot work on and near tanks, the CSB’s lesson was that the absence of flammables must be verified before and during the work, with a gas monitor that is calibrated and used by trained people.

Source: U.S. Chemical Safety Board, hot work safety bulletin

In UProcess Each type carries a gas plan with alarm and stop limits per gas. A reading at the alarm limit leaves the gas gate unmet, says which gas, and a reading at the stop limit suspends an active permit.

LEL at the work point · 12 Nov 2026

13:30
0% LEL
14:30
0% LEL
14:52
12% LEL

14:52 · 12% LEL · stop limit reached · permit suspended

Alarm 5% · Stop 10%

04

Two safe permits, one unsafe combination.

HSE guidance expects permits to coordinate activities so jobs do not conflict, and related permits to be linked where tasks run at the same time or depend on each other.

Source: HSE, human factors: permit to work

In UProcess Your compatibility rules set which activities may run together and at what distance. A prohibited pair cannot be authorised while the other permit is active, and two permits on the same tag always show each other.

Compatibility rules · Tank farm

Hot workDrain and ventGrit blasting
Hot work—Prohibited within 15 mAllowed with conditions
Drain and ventProhibited within 15 m—Allowed

PTW-2026-0147 drain and vent at T-202 is held while PTW-2026-0142 is active. Two permits on one tag always show each other.

Cutaway of the tank during the test: water below, a layer of fuel vapour above it, a welder at the roof edge.
Tank in section · the moment before ignition

Process accident case · Hydrostatic test

The pressure test with people still nearby.

The tank was new. The water was clean. The hazard came in with the hose.

· 2 injured · Trevor Kletz, What Went Wrong?

2Hot work permitThe record mentions no permit. The handrails were finished as routine work.Safe work practices
See the case →

Permit PTW-2026-0142 · 12 Nov 2026

TimePersonEventSignature
15:20Thiago Moreira
Resumed · gas 0% LEL, 8 of 8 gates met
Confirmed on device
15:12Ana Lima
Gas reading 0% LEL, work point and vapour space
Confirmed on device
14:52Ana Lima
Gas reading 12% LEL · stop limit · permit suspended
Not re-confirmed (sent offline)
14:30Ana Lima
Gas reading 0% LEL
Confirmed on device
07:30Thiago Moreira
Activated after gas 0% LEL
Confirmed on device
07:24Carlos Mendes
Accepted the permit and its conditions
Confirmed on device
07:22Thiago Moreira
Authorised · 8 of 8 gates met
Confirmed on device
06:50Carlos Mendes
Requested
Session

The record an auditor asks for.

A permit is evidence only if it shows what was true at the moment each person signed.

  • Every permit with its type version, and each gate with the reason it was met.
  • Each signature with its time, and whether it was confirmed on the device.
  • Gas readings with tester, instrument and position, and the limits they were read against.
  • Revalidations, suspensions and the hand-back, shift by shift.

What’s in a permit

Lifecycle
Requested → Prepared → Authorised → Active ⇄ Suspended → Handed back → Closed, or Cancelled before work starts. Every step records who, when and why.
Types
Each permit type is your company’s own, versioned, with its gates, precautions, gas plan and roles.
Gates
Field check, isolation held and proven, gas in range, named roles present, competence, contract eligibility, task assessment, rescue plan, no conflicting work.
Gas
Alarm and stop limits per gas, readings with tester, instrument and position, re-tests on the plan’s interval, by hand or from an attached monitor.
Board
Your uploaded site plan with pins for permits, isolations, confined-space entries and bypasses, and conflicts drawn between them. A list on the phone.

Questions

Can anyone override a gate?

No. A gate is met or it is not. If a legitimate job cannot meet it, the permit type is wrong for the job, and the type is changed as a new version.

What happens at the shift change?

Every active or suspended permit shows revalidation due to the incoming area authority. Revalidated, it carries on; not revalidated, it is suspended.

Do we need Training and Contractor Management?

No. Without them, the authoriser attests competence and eligibility with a signature, and the permit shows that it was attested, not checked by the system.

Who can stop the work?

Anyone with Work Control access at the site, viewers included. One tap, a short reason, and the permit is suspended.

Your next permit, signed with the plant in view.

Start free →No account needed to start. Keep your work when you’re ready.